Kernow Solar Park Case Study

Case study 13623

Name of Client and Location: Solar Century , Kernow Solar Park Cornwall Council
Project Value:
Duration of the Project: 2012
Services: Electrical Infrastructure, Balance of Plant
Market Sector: Solar Market Renewable Energy
Powersystems Fact: Powersystems celebrate 24 years as the UK’s first Independent Connection Provider.

Kernow Solar Park Farm

Powersystems were responsible for the design, installation, testing and commissioning of the electrical infrastructure associated with the construction of the 5 MW solar park, Kernow Solar Farm, St Mawgan near to Newquay Cornwall airport.

The Kernow Solar park scheme saw the development of a 5 MW solar park at St Mawgan, near to Newquay Cornwall airport, producing an initial income of around £700,000 per year and enough power to run 1,000 homes.

The plan for the solar park was to supply power to the national grid, but also directly to the Council owned Newquay Airport. This was to help to reduce the Airport’s carbon footprint and save money.

Both of the Point of Connections (POC) exported into the same WPD 11 kV network

Kernow Solar Park was a tangible demonstration of the Council’s tenacity and leadership. At that time, they were leading the way with their own development, showing full commitment to a Green Cornwall Strategy.

The Kernow Solar park project aimed to generate renewable electricity equivalent to almost 5 per cent of the Council’s carbon footprint.

The power supplied from the solar farm would greatly assist the Airport’s aspiration to make their operations carbon neutral, helping them to become one of the UK’s greenest airports. They were working towards certification through the Airports Council International (ACI) Carbon Accreditation Scheme and being able to source their electricity directly from the solar farm aimed to dramatically reduce their emissions.

Major design considerations:

The interconnection between the Newquay Airport 11,000v ring switchboard and the North site 1.5mw Solar Array invertor substation was made via a private wire 11,000v connection

The major items of electrical plant that Powersystems designed, supplied, installed, and commissioned were:

  • 11,000v cable pull between Newquay Airport substation and Solar Farm
  • 11,000v ring main unit and GRP substation building installation. Cable installation and terminating, earthing
  • Construct Substation Base
  • Supply, installation, testing and commissioning of Elster A1700 tariff metering
  • Extension of the Newquay Airport HV substation Airfield ring switchboard, and to provide import metering on the 11kv switchboard
  • HV Cable Trenching Works
  • Full installation test and commissioning

Project facts and figures:

  • Totalled Installed capacity: 5 MW
  • Solar farm Voltage: 11 kV
  • Connection Voltage: 11 kV
  • Length of onsite 11 kV cabling: 5 km
  • Powersystems are a Lloyds registered (NERS) approved independent connection provider (ICP)

Powersystems partnerships:

The Solar Farm was constructed by Solar Century

There is currently 1.5MW of solar PV connected between the Cornwall Airport Newquay and the solar farm via a private wire to the St Columb Major substation. This is sold to the airport at a slightly reduced rate of 15% on retail price. The private wire is rated to be able to take up to 6.7MW of capacity, and there is therefore the potential to increase the energy delivered to the Cornwall Airport Newquay.

There is also an additional southern grid connection to a second substation (St. Mawgan) which is currently where the remaining 3.5MW solar farm generation is exported to the electricity network using a separate PPA agreement

Project timings:

2012

What the client wanted:

Powersystems carried out the construction role for both the grid connection and private wire network and were appointed by Cornwall Council. Powersystems were utilised as the conduit between the client and WPD in gaining design approval for the substation, connection works and receiving WPD sign off for the build.

How Powersystems have helped:

Powersystems engineers were involved with the;

  • Interface with Western Power Distribution
  • Switchgear installation and commissioning
  • Transformer installation and commissioning
  • Cable design, supply & installation
  • HV testing
  • SAP provision

Environmental benefits

  • Renewable clean energy
  • Reduction in the Carbon Footprint of Newquay Airport

Economic benefits

  • During construction, materials sourced from local suppliers where possible
  • Local companies/resource employed where possible
  • Solar Farm could provide sufficient power for up to 1500 homes

To speak with Powersystems, please contact us by...

Phone

01454 318000

Email

enquiries@powersystemsuk.com

Talk

Request a call back

Powersystems UK Delivering Greener Power Solutions

Pin It on Pinterest

Share This

Share this post with your friends!