Powersystems completed the 1st energisation at the Clocaenog Forest Wind Turbine Farm 132kV compound with 2 Grid Transformers

Powersystems UK were appointed to design, supply installation, testing and commission a 132kV grid connection by Ruthin-based Jones Bros Civil Engineering UK who is the principal contractor and working closely with the Clocaenog Forest Wind Turbine Farm for developer innogy Renewables UK.

This marks a massive milestone in the renewable energy development project in Denbighshire to connect 27×3.6MW Vestas Wind Turbines. And further progress the £120 million scheme.

Powersystems have constructed the dual transformer 132kV substation to enable the 96MW of power generated from the wind turbines to be exported to the grid.

Within Clocaenog Forest itself, Powersystems the electrical engineering company has also laid 181km of 33kV power and fibre optic cable works to connect all 27×3.6MW Vestas Wind Turbines.

Managing Director Chris Jenkins said: “We’re proud to get to this milestone in the project and again, prove our capability to deliver for our clients.

“Operating at 132kV requires specialist capability and at Powersystems we have a track record of delivering projects at this high voltage level.

“Final connection works to the turbines continues and we see the completion of this over the summer of 2019, with first generation expected in June.

Powersystems UK, have installed the infrastructure for 3GW of Wind Farm generation across the UK representing 25% of on-shore windfarms built.

The wind farm, situated within the working forest managed by Natural Resources Wales, will have the capacity to generate enough electricity to meet the needs of up to 63,800 average UK homes per year.

For more information about the Clocaenog Wind Turbine Farm project please visit https://www.powersystemsuk.co.uk/project/15382-clocaenog-wind-farm/

For more information about Powersystems UK please visit the website www.powersystemsuk.co.uk

Notes To Editors – Contact Information

This article is written by Jules Daly, Marketing and Communications Manager at Powersystems UK. Email jules.daly@powersystemsuk.com Telephone 01454 318000

Photography Copyright please credit all images used to www.powersystemsuk.co.uk

Powersystems UK Ltd are a specialist High Voltage electrical engineering company established in 1977.  Our head office is located in Yate, Bristol. Our current turnover to December 2018 is in excess of £27 million, in 2019 we celebrate our 42nd year of trading.

Powersystems have grown by reputation to become a major force in the design and installation of high voltage infrastructure across the whole of the United Kingdom.

As one of the first Lloyds National Electricity Registration Scheme ‘s accredited Independent Connection Providers we are capable of delivering contestable grid connections at voltages up to 132kV.

We have supported and delivered projects for diverse clientele; this includes:

  • Dyson Hullavigton, electric vehicle research and development facility for UK electric vehicle production
  • Millbrook Proving Ground, electric vehicle testing facility
  • EV infrastructure, for bus transportation projects UK wide
  • Warner Bros Harry Potter Studio, London
  • Rolls Royce Aero Engines and Airbus
  • Jaguar Land Rover
  • Formula One Race Teams (Mercedes Petronas, Williams F1 and Red Bull Technologies)
  • Public Sector – Ministry of Defence, Universities, NHS Trusts UK wide, Schools, Water Utilities.
  • Bristol, Newport and Southampton Port Authorities

Powersystems UK Ltd. is an Employee Owned Business and as such has a keen interest in the well-being of all its employees. We encourage and empower you to be imaginative, share great ideas and be involved in the success of our business.

To speak with Powersystems, please contact us by...

Phone

01454 318000

Email

enquiries@powersystemsuk.com

Talk

Request a call back

Powersystems UK Delivering Greener Power Solutions

Pin It on Pinterest

Share This

Share this post with your friends!